The construction programme for Phase 1a:

  • Onshore civil works: January – July 2015
  • Horizontal Directional Drilling: March – June 2015
  • Turbine Subsea Cable installation: July – September 2015
  • Turbine Support Structures installation: July – September 2015
  • Turbine installation and commissioning: March – October 2016